HBH Vietnam — Vì chất lượng cuộc sống
Back to projects list
Chiller · AHU · BMSYEAR · 2020

Military Hospital 103 — Building A2

Supply & installation of 2,400 RT Chiller system, AHU, central BMS

Military Hospital 103 — Building A2
— TECHNICAL NOTES

Scope of work

Supply & installation of 2,400 RT Chiller system, AHU, central BMS. HBH acts as the M&E main contractor for the entire system, including site survey, shop drawing design, supply of genuine equipment, installation and operational handover on the main-contract schedule.

The system carries a 24-month warranty per manufacturer standards, with a periodic maintenance contract signed with HBH's dedicated engineering team.

Military Hospital 103 — Building A2 — 1Military Hospital 103 — Building A2 — 2Military Hospital 103 — Building A2 — 3